Work carried out with a deep propeller pile foundation and a shallow foundation with blocks and baldrames, with a conventional concrete structure of 22 floors and a reinforced concrete floor designed for vehicle traffic. At the entrance to the project, an aluminum grill with black electrostatic paint was used with glass and in the area of the gate, 10 mm polycarbonate with an armored gate built at level IIIA of standard NIJ 0108.1.

On the façade of the project, a metallic brise system was installed, a model with monolithic checkered grilles in white with a mesh of 150 x 150 mm between axes.

The project's garages consisted of finished concrete floors and where rain occurs, waterproofing was carried out with a 4 mm asphalt layer attached with oxidized asphalt and an asphalt bath, protected with concrete coating. In the garage on the 4th floor, in addition to the waterproofing system with asphalt blanket, a PU (polyurethane) protection system for self-traffic was used.

The project has a fire fighting system, equipped with a fire alarm, a ladder pressurization system and smoke detectors.

The condominium is equipped with an energy generator system and has acoustic insulation in its area.

PPR (Random Copolymer Polypropylene) plums were used for vertical feeding of hydraulic systems and Pex system (flexible cross-linked polyethylene tubing), both for the distribution of hot and cold water.

Gas is distributed to the units through buried pipes and in watertight or ventilated plumage identified according to standards established by Comgas. Inside the unit there are 2 forecasts for gas: one in the service area that is available for installation of the passage heater system and the other in the kitchen to forecast the stove.

The units are powered by the Busway system (shielded bus), together with a power cable to the main frame of the unit, protected by a DR circuit breaker.

The external walls of the units are composed of sealing masonry and the internal walls are composed of a drywall system, made of Standard plates and RU plates (moisture resistant).

In wet areas, a polymer waterproofing system was introduced with a 10 x 10 mm mesh reinforcement mesh.

In the pool area, the raised floor system was used to create the pool deck covered in granite stone.

The adult pool has been incorporated with an infinity edge system. To create this system, the entire perimeter of the edge was made 3 cm below the bank level, with the objective of creating a water slide, which dumps the excess water into a recirculation lung from the infinite edge. This excess of water that overflows and falls into the circulation lung is led to a water tank, located below the raised floor, which, with an automatic system of buoys and pumps, recirculates the water to the pool, thus creating a unique system.

The pool waterproofing system consisted of a double asphalt layer of 3 and 4 mm bonded with oxidized asphalt.

On the roof, lightning protection systems (SPDA) were built, connected to every project.

.